Belize wall-system comparison

Compare reinforced concrete block and Stelcor ICF.

Use one wall geometry to compare a standard reinforced CMU wall, the same CMU wall with added insulation, and Stelcor ICF. Quantities are calculated first; costs include only the current material rates shown below.

Planning model · BZ$ Current supplier rates are editable. Structural dimensions and reinforcement must be confirmed by the project engineer.

Project assumptions

Start with the exterior walls. This comparison does not estimate foundations, roofs, slabs, MEP, finishes or whole-building cost.

ft
ft
%
count
count

Used only to allow for reinforced CMU jamb columns.

6-inch is the supplier’s common-use starting point; engineering governs.

Confirm the actual Stelcor core and design with Stelcor and the engineer.

Quantity allowances

Visible planning assumptions from the research specification. They can be changed for the project.

%
%
%
BZ$/ft²
Review and edit current material rates
BZ$/ea
BZ$/ea
BZ$/ea
BZ$/yd³
BZ$/bag
bags/yd³

No default: the supplier confirmed bag sizes but not the approved mix ratio.

BZ$/bar
BZ$/bar

The supplier’s “concrete mix” is sand and gravel combined—not delivered concrete. The material subtotal prices that aggregate separately and adds cement only after a project mix dosage is entered.

Side-by-side planning result

All three systems use the same net exterior wall area. The CMU columns and bond beam are included so block is not compared as infill units alone.

1,360 ft² · 126.3 m²
System A

Reinforced CMU

Structural columns and bond beam, partially grouted block infill, no added insulation.

CMU units
RC columns
Concrete / grout
½-in steel · 40-ft bars
¼-in stirrup steel · 20-ft bars
CMU unit cost
Reinforcement cost
Concrete aggregate component
Concrete cement componentPending mix
Known material subtotalBefore mortar, formwork, labour, finishes, delivery, GST and any pending concrete cement.
Mortar usage and cost remain project inputs; no Belize rule was supplied.

Thermal basis: no insulation is included. A Stelcor-specific comparison should not assign a tested R-value to local 6-inch CMU without assembly data.

System B

Thermally upgraded CMU

The same reinforced CMU wall plus a user-priced insulation strategy over the net wall area.

CMU units
Insulation coverage
Concrete / grout
½-in steel · 40-ft bars
Base CMU materials
Insulation allowanceQuote required
Known material subtotalUses the same exclusions as System A; insulation is added only when a rate is entered.
Enter a supplied-and-installed insulation rate to complete this added line.

Thermal basis: performance depends on the selected insulation, continuity, fixings and finish. The tool does not invent an R-value.

What the subtotal means

It is the sum of the priced units shown: CMU or ICF forms, reinforcement, concrete aggregate, optional cement dosage and optional CMU insulation. It is not an installed wall price.

Hurricane comparison

Properly reinforced CMU and reinforced ICF can both form robust wall systems. Roof-to-wall connections, openings and the complete load path remain critical and require engineering.

Current Belize rates

Defaults use the supplied BZ price list: 6-inch block BZ$3.40, concrete mix BZ$95/yd³, Progreso 42.5 kg cement BZ$25, ½-inch steel BZ$44/40 ft and ¼-inch steel BZ$7/20 ft.

Preliminary planning comparison only. Quantities rely on visible assumptions and do not establish structural adequacy. Ballpark mode does not quantify opening lintels. Costs exclude mortar unless separately quoted, labour, formwork timber, finishes, drainage planes, bucks, termite treatment, pumping, delivery, remote-location premiums, GST, contingency, foundations, roofs, slabs and professional fees. Have Stelcor and the project engineer review the drawings and specifications before ordering or construction.

Send your plans for a detailed comparison